ProjectResourceFields={
    Accrual: 0, 
    ActualCost: 1, 
    ActualOvertimeCost: 2, 
    ActualOvertimeWork: 3, 
    ActualOvertimeWorkProtected: 4, 
    ActualWork: 5, 
    ActualWorkProtected: 6, 
    BaseCalendar: 7, 
    Baseline10BudgetCost: 8, 
    Baseline10BudgetWork: 9, 
    Baseline10Cost: 10, 
    Baseline10Work: 11, 
    Baseline1BudgetCost: 12, 
    Baseline1BudgetWork: 13, 
    Baseline1Cost: 14, 
    Baseline1Work: 15, 
    Baseline2BudgetCost: 16, 
    Baseline2BudgetWork: 17, 
    Baseline2Cost: 18, 
    Baseline2Work: 19, 
    Baseline3BudgetCost: 20, 
    Baseline3BudgetWork: 21, 
    Baseline3Cost: 22, 
    Baseline3Work: 23, 
    Baseline4BudgetCost: 24, 
    Baseline4BudgetWork: 25, 
    Baseline4Cost: 26, 
    Baseline4Work: 27, 
    Baseline5BudgetCost: 28, 
    Baseline5BudgetWork: 29, 
    Baseline5Cost: 30, 
    Baseline5Work: 31, 
    Baseline6BudgetCost: 32, 
    Baseline6BudgetWork: 33, 
    Baseline6Cost: 34, 
    Baseline6Work: 35, 
    Baseline7BudgetCost: 36, 
    Baseline7BudgetWork: 37, 
    Baseline7Cost: 38, 
    Baseline7Work: 39, 
    Baseline8BudgetCost: 40, 
    Baseline8BudgetWork: 41, 
    Baseline8Cost: 42, 
    Baseline8Work: 43, 
    Baseline9BudgetCost: 44, 
    Baseline9BudgetWork: 45, 
    Baseline9Cost: 46, 
    Baseline9Work: 47, 
    BaselineBudgetCost: 48, 
    BaselineBudgetWork: 49, 
    BaselineCost: 50, 
    BaselineWork: 51, 
    BudgetCost: 52, 
    BudgetWork: 53, 
    ResourceCalendarGUID: 54, 
    Code: 55, 
    Cost1: 56, 
    Cost10: 57, 
    Cost2: 58, 
    Cost3: 59, 
    Cost4: 60, 
    Cost5: 61, 
    Cost6: 62, 
    Cost7: 63, 
    Cost8: 64, 
    Cost9: 65, 
    ResourceCreationDate: 66, 
    Date1: 67, 
    Date10: 68, 
    Date2: 69, 
    Date3: 70, 
    Date4: 71, 
    Date5: 72, 
    Date6: 73, 
    Date7: 74, 
    Date8: 75, 
    Date9: 76, 
    Duration1: 77, 
    Duration10: 78, 
    Duration2: 79, 
    Duration3: 80, 
    Duration4: 81, 
    Duration5: 82, 
    Duration6: 83, 
    Duration7: 84, 
    Duration8: 85, 
    Duration9: 86, 
    Email: 87, 
    End: 88, 
    Finish1: 89, 
    Finish10: 90, 
    Finish2: 91, 
    Finish3: 92, 
    Finish4: 93, 
    Finish5: 94, 
    Finish6: 95, 
    Finish7: 96, 
    Finish8: 97, 
    Finish9: 98, 
    Flag10: 99, 
    Flag1: 100, 
    Flag11: 101, 
    Flag12: 102, 
    Flag13: 103, 
    Flag14: 104, 
    Flag15: 105, 
    Flag16: 106, 
    Flag17: 107, 
    Flag18: 108, 
    Flag19: 109, 
    Flag2: 110, 
    Flag20: 111, 
    Flag3: 112, 
    Flag4: 113, 
    Flag5: 114, 
    Flag6: 115, 
    Flag7: 116, 
    Flag8: 117, 
    Flag9: 118, 
    Group: 119, 
    Units: 120, 
    Name: 121, 
    Notes: 122, 
    Number1: 123, 
    Number10: 124, 
    Number11: 125, 
    Number12: 126, 
    Number13: 127, 
    Number14: 128, 
    Number15: 129, 
    Number16: 130, 
    Number17: 131, 
    Number18: 132, 
    Number19: 133, 
    Number2: 134, 
    Number20: 135, 
    Number3: 136, 
    Number4: 137, 
    Number5: 138, 
    Number6: 139, 
    Number7: 140, 
    Number8: 141, 
    Number9: 142, 
    OvertimeCost: 143, 
    OvertimeRate: 144, 
    OvertimeWork: 145, 
    PercentWorkComplete: 146, 
    CostPerUse: 147, 
    Generic: 148, 
    OverAllocated: 149, 
    RegularWork: 150, 
    RemainingCost: 151, 
    RemainingOvertimeCost: 152, 
    RemainingOvertimeWork: 153, 
    RemainingWork: 154, 
    ResourceGUID: 155, 
    Cost: 156, 
    Work: 157, 
    Start: 158, 
    Start1: 159, 
    Start10: 160, 
    Start2: 161, 
    Start3: 162, 
    Start4: 163, 
    Start5: 164, 
    Start6: 165, 
    Start7: 166, 
    Start8: 167, 
    Start9: 168, 
    StandardRate: 169, 
    Text1: 170, 
    Text10: 171, 
    Text11: 172, 
    Text12: 173, 
    Text13: 174, 
    Text14: 175, 
    Text15: 176, 
    Text16: 177, 
    Text17: 178, 
    Text18: 179, 
    Text19: 180, 
    Text2: 181, 
    Text20: 182, 
    Text21: 183, 
    Text22: 184, 
    Text23: 185, 
    Text24: 186, 
    Text25: 187, 
    Text26: 188, 
    Text27: 189, 
    Text28: 190, 
    Text29: 191, 
    Text3: 192, 
    Text30: 193, 
    Text4: 194, 
    Text5: 195, 
    Text6: 196, 
    Text7: 197, 
    Text8: 198, 
    Text9: 199
 }

Members

The ProjectResourceFields enumeration contains the following members.

Name Value Description
Accrual 0 The accrual method that defines how a task accrues the cost of the resource: Accrues when the task starts = 1, accrues when the task ends = 2, accrues as the task progresses (prorated) = 3.
ActualCost 1 The calculated actual cost of the resource for assignments in the project.
ActualOvertimeCost 2 The actual overtime cost for a resource.
ActualOvertimeWork 3 The actual overtime work for a resource, in minutes.
ActualOvertimeWorkProtected 4 The actual overtime work for the resource that has been protected (made read-only).
ActualWork 5 The actual work that the resource has done on assignments in the project.
ActualWorkProtected 6 The actual work for the resource that has been protected (made read-only).
BaseCalendar 7 The name of the base calendar for the resource.
Baseline10BudgetCost 8 The budget cost for the baseline resource.
Baseline10BudgetWork 9 The budget work for the baseline resource, in hours.
Baseline10Cost 10 The cost for the baseline resource.
Baseline10Work 11 The work for the baseline resource, in minutes.
Baseline1BudgetCost 12 The budget cost for the baseline resource.
Baseline1BudgetWork 13 The budget work for the baseline resource, in hours.
Baseline1Cost 14 The cost for the baseline resource.
Baseline1Work 15 The work for the baseline resource, in minutes.
Baseline2BudgetCost 16 The budget cost for the baseline resource.
Baseline2BudgetWork 17 The budget work for the baseline resource, in hours.
Baseline2Cost 18 The cost for the baseline resource.
Baseline2Work 19 The work for the baseline resource, in minutes.
Baseline3BudgetCost 20 The budget cost for the baseline resource.
Baseline3BudgetWork 21 The budget work for the baseline resource, in hours.
Baseline3Cost 22 The cost for the baseline resource.
Baseline3Work 23 The work for the baseline resource, in minutes.
Baseline4BudgetCost 24 The budget cost for the baseline resource.
Baseline4BudgetWork 25 The budget work for the baseline resource, in hours.
Baseline4Cost 26 The cost for the baseline resource.
Baseline4Work 27 The work for the baseline resource, in minutes.
Baseline5BudgetCost 28 The budget cost for the baseline resource.
Baseline5BudgetWork 29 The budget work for the baseline resource, in hours.
Baseline5Cost 30 The cost for the baseline resource.
Baseline5Work 31 The work for the baseline resource, in minutes.
Baseline6BudgetCost 32 The budget cost for the baseline resource.
Baseline6BudgetWork 33 The budget work for the baseline resource, in hours.
Baseline6Cost 34 The cost for the baseline resource.
Baseline6Work 35 The work for the baseline resource, in minutes.
Baseline7BudgetCost 36 The budget cost for the baseline resource.
Baseline7BudgetWork 37 The budget work for the baseline resource, in hours.
Baseline7Cost 38 The cost for the baseline resource.
Baseline7Work 39 The work for the baseline resource, in minutes.
Baseline8BudgetCost 40 The budget cost for the baseline resource.
Baseline8BudgetWork 41 The budget work for the baseline resource, in hours.
Baseline8Cost 42 The cost for the baseline resource.
Baseline8Work 43 The work for the baseline resource, in minutes.
Baseline9BudgetCost 44 The budget cost for the baseline resource.
Baseline9BudgetWork 45 The budget work for the baseline resource, in hours.
Baseline9Cost 46 The cost for the baseline resource.
Baseline9Work 47 The work for the baseline resource, in minutes.
BaselineBudgetCost 48 The budget cost for the baseline resource.
BaselineBudgetWork 49 The budget work for the baseline resource, in hours.
BaselineCost 50 The baseline cost for the resource for assignments in the project.
BaselineWork 51 The baseline work for the resource for assignments in the project, in minutes.
BudgetCost 52 The budget cost for the resource.
BudgetWork 53 The budget work for the resource.
ReourceCalendarGUID 54 The GUID of the resource calendar.
Code 55 The code value of the resource.
Cost1 56 A cost field for the resource.
Cost10 57 A cost field for the resource.
Cost2 58 A cost field for the resource.
Cost3 59 A cost field for the resource.
Cost4 60 A cost field for the resource.
Cost5 61 A cost field for the resource.
Cost6 62 A cost field for the resource.
Cost7 63 A cost field for the resource.
Cost8 64 A cost field for the resource.
Cost9 65 A cost field for the resource.
ReourceCreationDate 66 The date the resource was created.
Date1 67 A date field for the resource.
Date10 68 A date field for the resource.
Date2 69 A date field for the resource.
Date3 70 A date field for the resource.
Date4 71 A date field for the resource.
Date5 72 A date field for the resource.
Date6 73 A date field for the resource.
Date7 74 A date field for the resource.
Date8 75 A date field for the resource.
Date9 76 A date field for the resource.
Duration1 77 A duration field for the resource.
Duration10 78 A duration field for the resource.
Duration2 79 A duration field for the resource.
Duration3 80 A duration field for the resource.
Duration4 81 A duration field for the resource.
Duration5 82 A duration field for the resource.
Duration6 83 A duration field for the resource.
Duration7 84 A duration field for the resource.
Duration8 85 A duration field for the resource.
Duration9 86 A duration field for the resource.
Email 87 The email address of the resource.
End 88 The end date of the resource availability.
Finish1 89 A finish field for the task.
Finish10 90 A finish field for the task.
Finish2 91 A finish field for the task.
Finish3 92 A finish field for the task.
Finish4 93 A finish field for the task.
Finish5 94 A finish field for the task.
Finish6 95 A finish field for the task.
Finish7 96 A finish field for the task.
Finish8 97 A finish field for the task.
Finish9 98 A finish field for the task.
Flag10 99 A Boolean flag field for the resource.
Flag1 100 A Boolean flag field for the resource.
Flag11 101 A Boolean flag field for the resource.
Flag12 102 A Boolean flag field for the resource.
Flag13 103 A Boolean flag field for the resource.
Flag14 104 A Boolean flag field for the resource.
Flag15 105 A Boolean flag field for the resource.
Flag16 106 A Boolean flag field for the resource.
Flag17 107 A Boolean flag field for the resource.
Flag18 108 A Boolean flag field for the resource.
Flag19 109 A Boolean flag field for the resource.
Flag2 110 A Boolean flag field for the resource.
Flag20 111 A Boolean flag field for the resource.
Flag3 112 A Boolean flag field for the resource.
Flag4 113 A Boolean flag field for the resource.
Flag5 114 A Boolean flag field for the resource.
Flag6 115 A Boolean flag field for the resource.
Flag7 116 A Boolean flag field for the resource.
Flag8 117 A Boolean flag field for the resource.
Flag9 118 A Boolean flag field for the resource.
Group 119 The group the resource belongs to.
Units 120 The percentage of work units that the resource has assigned in the project. If the resource is working full-time on the project, Units = 100.
Name 121 The name of the resource.
Notes 122 The text value of the notes regarding the resource.
Number1 123 A number field for the resource.
Number10 124 A number field for the resource.
Number11 125 A number field for the resource.
Number12 126 A number field for the resource.
Number13 127 A number field for the resource.
Number14 128 A number field for the resource.
Number15 129 A number field for the resource.
Number16 130 A number field for the resource.
Number17 131 A number field for the resource.
Number18 132 A number field for the resource.
Number19 133 A number field for the resource.
Number2 134 A number field for the resource.
Number20 135 A number field for the resource.
Number3 136 A number field for the resource.
Number4 137 A number field for the resource.
Number5 138 A number field for the resource.
Number6 139 A number field for the resource.
Number7 140 A number field for the resource.
Number8 141 A number field for the resource.
Number9 142 A number field for the resource.
OvertimeCost 143 The overtime cost for a resource.
OvertimeRate 144 The overtime rate for a resource.
OvertimeWork 145 The overtime work for a resource.
PercentWorkComplete 146 The percentage of work complete for a resource.
CostPerUse 147 The cost per use of the resource.
Generic 148 Indicates whether the resource is a generic resource (identified by skill rather than by name).
OverAllocated 149 Indicates whether the resource is overallocated.
RegularWork 150 The amount of regular work for the resource.
RemainingCost 151 The remaining cost for the resource.
RemainingOvertimeCost 152 The remaining overtime cost for the resource.
RemainingOvertimeWork 153 The remaining overtime work for the resource, in minutes.
RemainingWork 154 The remaining work for the resource, in minutes.
ResourceGUID 155 The ID of the resource.
Cost 156 The total cost of the resource.
Work 157 The total work for the resource, in minutes.
Start 158 The start date for the resource.
Start1 159 A start field for the resource.
Start10 160 A start field for the resource.
Start2 161 A start field for the resource.
Start3 162 A start field for the resource.
Start4 163 A start field for the resource.
Start5 164 A start field for the resource.
Start6 165 A start field for the resource.
Start7 166 A start field for the resource.
Start8 167 A start field for the resource.
Start9 168 A start field for the resource.
StandardRate 169 The standard rate of pay for the resource, in cost per hour.
Text1 170 A text field for the resource.
Text10 171 A text field for the resource.
Text11 172 A text field for the resource.
Text12 173 A text field for the resource.
Text13 174 A text field for the resource.
Text14 175 A text field for the resource.
Text15 176 A text field for the resource.
Text16 177 A text field for the resource.
Text17 178 A text field for the resource.
Text18 179 A text field for the resource.
Text19 180 A text field for the resource.
Text2 181 A text field for the resource.
Text20 182 A text field for the resource.
Text21 183 A text field for the resource.
Text22 184 A text field for the resource.
Text23 185 A text field for the resource.
Text24 186 A text field for the resource.
Text25 187 A text field for the resource.
Text26 188 A text field for the resource.
Text27 189 A text field for the resource.
Text28 190 A text field for the resource.
Text29 191 A text field for the resource.
Text3 192 A text field for the resource.
Text30 193 A text field for the resource.
Text4 194 A text field for the resource.
Text5 195 A text field for the resource.
Text6 196 A text field for the resource.
Text7 197 A text field for the resource.
Text8 198 A text field for the resource.
Text9 199 A text field for the resource.

Remarks

A ProjectResourceFields constant can be used as a parameter of the getResourceFieldAsync method.

For more information about working with fields in Project, see Available fields reference. In Project Help, search for Available fields.

Support details

A capital Y in the following matrix indicates that this enumeration is supported in the corresponding Office host application. An empty cell indicates that the Office host application doesn't support this enumeration.

For more information about Office host application and server requirements, see Requirements for running Office Add-ins.

Supported hosts, by platform

Office for Windows desktop Office Online (in browser)
Project Y
Add-in types Task pane
Library Office.js
Namespace Office

Support history

Version Changes
1.0 Introduced

See also

Other resources

getResourceFieldAsync method

Available fields reference